Louds Mill Fish Pass Construction

The concreting of the floor and walls of the fish pass slot is now complete (see attached pics), with the formwork for the walls being removed today. The work continues to progress as programmed.

Next week they will be installing the formwork and pouring the concrete for the slope that the top of the fish pass will end up sitting on.


Report by
Andy Martin
Fisheries Technical Specialist
Environment Agency